Estimates of appropriations

Vote Energy - Estimates of Appropriations 2012/13 - Estimates 2012/2013

Formats and related files

MINISTER(S) RESPONSIBLE FOR APPROPRIATIONS: Minister for Climate Change Issues (M12), Minister of Energy and Resources (M28)

ADMINISTERING DEPARTMENT: Ministry of Economic Development

MINISTER RESPONSIBLE FOR MINISTRY OF ECONOMIC DEVELOPMENT: Minister for Economic Development

Overview of the Vote#

The Minister of Energy and Resources is responsible for appropriations in the Vote for the 2012/13 financial year covering the following:

  • a total of just over $6.500 million for policy advice on the operation and information disclosure of energy resource markets, services to support the Minister, and monitoring the performance and compliance of Crown entities
  • a total of just over $13.900 million for the management of the Crown mineral estate
  • a total of just over $5.600 million for the administration of the gas, and electrical safety regime, this is an industry levy funded activity
  • a total of just under $2.900 million for the provision of information and technical advice on energy and resources, the management of the response to any international disruption in oil supplies, and the management of New Zealand's energy-related international relations
  • a total of just over $63.900 million for the Electricity Authority's work in regulating the electricity system, this is an industry levy funded activity
  • a total of just over $38 million for the Energy Efficiency and Conservation Authority's work in promoting energy efficiency, and by providing grants and assistance of a forecast $71 million for the Warm Up New Zealand: Heat Smart programme in 2012/13
  • a total of $3.500 million in the third year of a four year multi-year appropriation for facilitating and promoting increased switching between suppliers by electricity consumers
  • a total of $1.200 million for the management of emergency events by the electricity System Operator, including increased monitoring and management responsibilities in the event of an emerging security situation, and planning and running an emergency conservation campaign
  • a total of just over $5 million to manage and fund New Zealand's oil stocks obligations with the International Energy Agency
  • a total of $519,000 for international membership fees, and to meet Ministry of Energy residual liabilities in regards to urgent mine restoration and rehabilitation relating to the operations of the state coal mines prior to 1987
  • a total of $2.490 million for the contestable fund for deployment of marine energy devices, and for enabling the repair of housing at Ratana to a standard that enables the installation of clean-heating devices and insulation, and
  • a total of $1.100 million for to assist the decommissioning of high-emission heating options to improve air quality in polluted airsheds.

The Ministry expects to collect just under $471 million of Crown revenue in 2012/13 which is mainly made up of:

  • a total of just under $346 million from petroleum royalties
  • a total of just over $80 million in levies from the Electricity Industry, and
  • a total of just under $36 million from coal and gas energy resource levies.

Details of these appropriations are set out in Parts 2-6 for Vote Energy in the Information Supporting the Estimates of Appropriations.

Details of Appropriations#

Details of Annual and Permanent Appropriations

Details of Annual and Permanent Appropriations - Energy
  2011/12 2012/13
Titles and Scopes of Appropriations by Appropriation Type Budgeted
$000
Estimated
Actual
$000
Budget
$000

Departmental Output Expenses

     

Administration of Gas, Electricity and Energy Efficiency Regulations and Related Acts (M28)

This appropriation is limited to the purchase of advice on administration and associated policy work, Ministerial servicing and decision support for the Minister in relation to, and the administration of the regimes for: gas and electricity safety; energy efficiency and conservation; the supply, quality and measurement of gas and electricity; and fuel quality monitoring.
5,130 4,458 5,680

Energy and Resource Information Services (M28)

Provision of information and technical advice on energy and resources, the management of the response to any international disruption in oil supplies, and the management of New Zealand's energy-related international relations.
4,333 3,468 1,067

Energy and Resource Information Services RDA (M28)

Provision of information and technical advice on energy and resources, the management of the response to any international disruption in oil supplies, and the management of New Zealand's energy-related international relations.
1,827 1,284 1,827

Energy and Resources Operational Policy, Ministerial Servicing and Crown Entity Monitoring (M28)

This appropriation is limited to the development of operational policies in relation to the operation of energy and resource markets (electricity, oil, gas, geothermal, coal, minerals and natural related resources) and energy efficiency and conservation issues, services to support the Minister, and monitoring the performance and compliance of Crown Entities.
- - 1,517

Management of the Crown Mineral Estate (M28)

Allocation and management of Crown-owned petroleum, coal and mineral resources under the Crown Minerals Act 1991 and minerals programmes issued under the Act.
15,108 13,918 13,963

Policy Advice - Energy and Resource Issues (M28)

This appropriation is limited to the provision of advice (including second opinion advice and contributions to policy advice led by other agencies) to support decision-making by Ministers on government policy matters.
- - 5,010

Emissions Trading Implementation (M12)

This appropriation is limited to the implementation and administration of the New Zealand Emissions Trading Scheme.
1,634 1,618 -

Policy Advice on Energy and Resource Issues (M28)

This appropriation is limited to the purchase of policy advice, ministerial servicing, and decision support for the Minister in relation to the operation of energy and resource markets (electricity, oil, gas, geothermal, coal, minerals and related natural resources) and energy efficiency and conservation issues, including Treaty of Waitangi issues in relation to natural resources in particular mineral and energy resources. It also includes purchase of ownership and purchase advice on Crown entities.
6,619 6,078 -

Provision of Climate Change Unit Register and Information (M12)

This appropriation is limited to services relating to the operation of a register to enable the allocation and trading of climate change units under the Climate Change Response Act 2002.
524 520 -

Total Departmental Output Expenses

35,175 31,344 29,064

Non-Departmental Output Expenses

     

Electricity Industry Governance and Market Operations (M28)

This appropriation is limited to formulating, monitoring and enforcing compliance with the regulations and rules governing the electricity industry and other outputs in accordance with the statutory functions under the Electricity Industry Act; and delivery of core electricity system and market operation functions, carried out under service provider contracts.
62,535 62,535 63,906

Energy Efficiency and Conservation MCOA (M28)

38,246 38,246 37,344
Electricity Efficiency
This output class is limited to:
- conducting electricity efficiency research, and
- development and administration of programmes that provide incentives for cost-effective energy efficiency and conservation, aimed at changing market behaviours.
13,000 13,000 13,000
Energy Efficiency and Conservation
This output class is limited to operational and policy outputs in accordance with statutory functions under the Energy Efficiency and Conservation Act 2000 and the government's energy strategies.
25,246 25,246 24,344

Maintenance and Operation of Whirinaki (M28)

Largely fixed operating and maintenance costs for Whirinaki power station including the Contact Operating and Maintenance contract, depreciation on the plant and obligations arising under the Reserve Generation Capacity Agreement.
2,600 2,600 600

Management of IEA Oil Stocks (M28)

For the cost of managing and funding of oil stocks to meet International Energy Agency obligations.
3,000 2,638 5,160

Reserve Energy and Emergency Measures-Availability Costs (M28)

Funds the cost of having reserve electricity capacity and capability available, including:
1. tendering for reserve energy and emergency options; and
2. ensuring availability of reserve energy capacity.
Does not include cost of supply of reserve energy (fuel) or implementation of emergency measures.
10,670 10,670 -

Total Non-Departmental Output Expenses

117,051 116,689 107,010

Non-Departmental Other Expenses

     

Air Quality Grants and Assistance (M28)

This appropriation is limited to assistance for the decommissioning of high-emission heating options to improve air quality in polluted airsheds.
1,100 1,100 1,100

Electricity Litigation Fund (M28)

This appropriation is limited to ensuring that the regulatory body for the electricity industry is able to participate in litigation effectively and without delay.
444 444 444

Energy Efficiency and Renewable Energy Grants and Assistance (M28)

This appropriation is limited to the Crown's contribution to fund improvements to the energy efficiency of New Zealand businesses and homes and increased use of renewable energy.
1,950 1,950 680

International Energy Agency Contribution (M28)

Payment of contributions towards the cost of energy-related research undertaken by the International Energy Agency.
150 132 150

International Energy Agency Subscription (M28)

Payment of annual subscription for membership of the International Energy Agency.
170 170 170

Ministry of Energy Residual Liabilities (M28)

Payment of residual liabilities of the former Ministry of Energy and to meet urgent mine restoration and rehabilitation relating to the operations of the state coal mines prior to 1987.
199 25 199

Biodiesel Grants (M28)

This appropriation is limited to the provision of grants to New Zealand biodiesel producers.
800 800 -

Crown Contribution to Pike River Recovery and Related Matters (M28)

This appropriation is limited to providing a Crown contribution towards the potential recovery of bodies in the Pike River Coal Mine and related matters.
5,000 5,000 -

Total Non-Departmental Other Expenses

9,813 9,621 2,743

Non-Departmental Capital Expenditure

     

Crown Energy Efficiency (M28)

This capital expenditure appropriation is limited to provision of funding for the Crown loans scheme to assist public sector agencies in implementing energy efficiency projects.
2,000 2,000 2,000

Total Non-Departmental Capital Expenditure

2,000 2,000 2,000

Total Annual and Permanent Appropriations

164,039 159,654 140,817

Details of Multi-Year Appropriations#

Multi-Year Appropriations - Energy
Type, Title, Scope and Period of Appropriations Appropriation, Adjustments and Use $000

Non-Departmental Output Expenses

   

Acquisition of Petroleum Exploration Data (M28)

This appropriation is limited to the acquisition of seismic information relating to New Zealand’s offshore petroleum basins.

Commences: 1 July 2009

Expires: 30 June 2014

Original Appropriation 20,000
Adjustments for 2010/11 -
Adjustments to 2011/12 -
Adjusted Appropriation 20,000
Actual to 2010/11 Year End 14,124
Estimated Actual for 2011/12 3,876
Estimated Actual for 2012/13 -
Estimated Appropriation Remaining 2,000

Generating Reserve Electricity At Whirinaki (M28)

To cover Whirinaki Reserve Energy Plant security of supply costs, excluding those covered by the annual appropriation entitled Maintenance and Operation of Whirinaki. Predominantly expected to cover purchase of fuel against the event that the plant is required to generate reserve electricity.

Commences: 1 July 2007

Expires: 30 June 2012

Original Appropriation 49,045
Adjustments for 2010/11 94,956
Adjustments to 2011/12 -
Adjusted Appropriation 144,001
Actual to 2010/11 Year End 33,768
Estimated Actual for 2011/12 5,340
Estimated Actual for 2012/13 -
Estimated Appropriation Remaining 104,893

Reserve Energy and Emergency Measures - Variable (M28)

To cover Electricity Commission costs relating to the: 1. net variable operating costs of the Whirinaki Reserve Energy Plant when used to provide reserve energy, and 2. implementation of emergency measures.

Commences: 1 July 2007

Expires: 30 June 2012

Original Appropriation 5,000
Adjustments for 2010/11 (4,750)
Adjustments to 2011/12 (43)
Adjusted Appropriation 207
Actual to 2010/11 Year End (2,358)
Estimated Actual for 2011/12 -
Estimated Actual for 2012/13 -
Estimated Appropriation Remaining 2,565

Reserve Energy and Emergency Measures - Variable Costs (M28)

This appropriation is limited to net variable operating costs of the Whirinaki Reserve Energy Plant when used to provide reserve energy; and implementation of emergency measures.

Commences: 1 November 2010

Expires: 30 June 2012

Original Appropriation 4,867
Adjustments for 2010/11 -
Adjustments to 2011/12 -
Adjusted Appropriation 4,867
Actual to 2010/11 Year End 205
Estimated Actual for 2011/12 -
Estimated Actual for 2012/13 -
Estimated Appropriation Remaining 4,662

Security Management (M28)

This appropriation is limited to the management of emergency events by the System Operator, if required, including increased monitoring and management responsibilities in the event of an emerging security situation, and planning and running an emergency conservation campaign.

Commences: 1 July 2012

Expires: 30 June 2017

Original Appropriation 6,000
Adjustments for 2010/11 (2,400)
Adjustments to 2011/12 1,200
Adjusted Appropriation 4,800
Actual to 2010/11 Year End -
Estimated Actual for 2011/12 -
Estimated Actual for 2012/13 1,200
Estimated Appropriation Remaining 3,600

Non-Departmental Other Expenses

   

Contestable Fund for Deployment of Marine Energy Devices (M28)

This appropriation is limited to a contestable fund for marine energy generation and associated administration.

Commences: 1 July 2011

Expires: 30 June 2016

Original Appropriation 4,949
Adjustments for 2010/11 -
Adjustments to 2011/12 (1,852)
Adjusted Appropriation 3,097
Actual to 2010/11 Year End -
Estimated Actual for 2011/12 1,143
Estimated Actual for 2012/13 780
Estimated Appropriation Remaining 1,174

Promoting and Facilitating Customer Switching (M28)

This appropriation is limited to facilitating, and promoting increased switching of electricity suppliers to consumers.

Commences: 1 November 2010

Expires: 30 April 2014

Original Appropriation 10,500
Adjustments for 2010/11 -
Adjustments to 2011/12 -
Adjusted Appropriation 10,500
Actual to 2010/11 Year End 1,499
Estimated Actual for 2011/12 3,501
Estimated Actual for 2012/13 3,500
Estimated Appropriation Remaining 2,000

Ratana Housing Repairs (M28)

This appropriation is limited to the repair of housing at Ratana to a standard which improves the overall safety and energy efficiency of the house and enables the installation of clean-heating devices and insulation.

Commences: 6 December 2010

Expires: 30 June 2013

Original Appropriation 2,060
Adjustments for 2010/11 -
Adjustments to 2011/12 -
Adjusted Appropriation 2,060
Actual to 2010/11 Year End -
Estimated Actual for 2011/12 350
Estimated Actual for 2012/13 1,710
Estimated Appropriation Remaining -

Warm Up New Zealand (M28)

This appropriation is limited to grants towards insulation and clean heating devices to make New Zealand homes healthier and more energy efficient.

Commences: 1 January 2010

Expires: 30 June 2014

Original Appropriation 244,950
Adjustments for 2010/11 32,118
Adjustments to 2011/12 (2,000)
Adjusted Appropriation 275,068
Actual to 2010/11 Year End 99,695
Estimated Actual for 2011/12 72,534
Estimated Actual for 2012/13 71,476
Estimated Appropriation Remaining 31,363