Formats and related files
Vote Prime Minister and Cabinet#
APPROPRIATION MINISTER(S): Minister of Civil Defence (M11), Prime Minister (M52), Minister for Greater Christchurch Regeneration (M85), Minister Responsible for the Earthquake Commission (M86)
APPROPRIATION ADMINISTRATOR: Department of the Prime Minister and Cabinet
RESPONSIBLE MINISTER FOR DEPARTMENT OF THE PRIME MINISTER AND CABINET: Prime Minister
Details of Appropriations and Capital Injections#
Annual and Permanent Appropriations#
2017/18 | |||
---|---|---|---|
Titles and Scopes of Appropriations by Appropriation Type | Estimates Budget $000 |
Supplementary Estimates Budget $000 |
Total Budget $000 |
Departmental Output Expenses |
|||
Canterbury Earthquake Recovery (M85) This appropriation is limited to provision of services supporting the regeneration of greater Christchurch. |
12,030 | 160 | 12,190 |
Support for Inquiry into EQC (M86) This appropriation is limited to supporting the Inquiry into EQC. |
- | 592 | 592 |
Total Departmental Output Expenses |
12,030 | 752 | 12,782 |
Departmental Capital Expenditure |
|||
Department of the Prime Minister and Cabinet - Capital Expenditure PLA (M52) This appropriation is limited to the purchase or development of assets by and for the use of the Department of the Prime Minister and Cabinet, as authorised by section 24(1) of the Public Finance Act 1989. |
300 | 250 | 550 |
Total Departmental Capital Expenditure |
300 | 250 | 550 |
Non-Departmental Other Expenses |
|||
Contributions to Local Authorities Following an Emergency Event (M11) This appropriation is limited to contributions to local authorities (other than contributions authorised by section 115A of the Civil Defence Emergency Management Act 2002) following an emergency event, as prescribed in the current Guide to the National Civil Defence Emergency Management Plan. |
- | 580 | 580 |
Crown Contribution for Christ Church Cathedral Reinstatement (M85) This appropriation is limited to provision of a Crown contribution towards the reinstatement of Christ Church Cathedral. |
- | 10,000 | 10,000 |
Emergency Expenses (M11) This appropriation is limited to payments to local authorities as provided for under the National CDEM Plan. |
2,000 | (2,000) | - |
Emergency Management Preparedness Grants (M11) This appropriation is limited to projects endorsed by CDEM Groups and managed or supported by the Ministry of Civil Defence & Emergency Management. |
889 | 152 | 1,041 |
Ex gratia payment to the University of Auckland (M52) This appropriation is limited to ex gratia payments to the University of Auckland to enable continued support of Professor Sir Peter Gluckman's own specialised research programme during his membership of the Science Advisory Committee. |
120 | - | 120 |
Fair Value Write-down of Suspensory Loan for Christ Church Cathedral Reinstatement (M85) This appropriation is limited to fair value write-down of the suspensory loan for the reinstatement of Christ Church Cathedral, in accordance with generally accepted accounting practice. |
- | 15,000 | 15,000 |
Governor-General's Programme PLA (M52) This appropriation is limited to expenses incurred on the Governor-General's Programme, as authorised by section 13 of the Governor-General Act 2010. |
1,139 | 100 | 1,239 |
Governor-General's Salary and Allowance PLA (M52) This appropriation is limited to expenses incurred on the salary, allowance and other payments to the Governor-General, as authorised by section 12 of the Governor-General Act 2010. |
400 | 100 | 500 |
Governor-General's travel outside New Zealand PLA (M52) This appropriation is limited to expenses incurred on the Governor-General's travel outside New Zealand, as authorised by section 14 of the Governor-General Act 2010. |
307 | 100 | 407 |
Inquiry into EQC (M86) This appropriation is limited to the payment of fees and expenses for the Inquiry into EQC. |
- | 216 | 216 |
Local Authority Emergency Expenses PLA (M11) This appropriation is limited to reimbursing a local authority for, or meeting, expenses incurred by a local authority in connection with an emergency as authorised by section 115A of the Civil Defence Emergency Management Act 2002. |
5,000 | 10,000 | 15,000 |
Rehabilitation of Kaikoura Harbour (M11) This appropriation is limited to a contribution to the Kaikoura District Council acting on behalf of Environment Canterbury for work necessary to restore the functionality of Kaikoura Harbour. |
720 | 1,750 | 2,470 |
Remuneration of Commissioners of Intelligence Warrants PLA (M52) This appropriation is limited to the salaries and allowances of Commissioners of Intelligence Warrants as authorised by clause 3(1) of Schedule 3 of the Intelligence and Security Act 2017. |
74 | 100 | 174 |
Restoration of Kaikoura District Three Waters Network (M11) This appropriation is limited to a contribution to Kaikoura District Council to support additional resilience, capacity, improved materials, or other alternatives to the original infrastructure as part of restoration of essential infrastructure systems. |
1,800 | 600 | 2,400 |
Total Non-Departmental Other Expenses |
12,449 | 36,698 | 49,147 |
Non-Departmental Capital Expenditure |
|||
Suspensory Loan for Christ Church Cathedral Reinstatement (M85) This appropriation is limited to provision of a suspensory loan for the reinstatement of Christ Church Cathedral. |
- | 15,000 | 15,000 |
Total Non-Departmental Capital Expenditure |
- | 15,000 | 15,000 |
Multi-Category Expenses and Capital Expenditure |
|||
Emergency Management MCA (M11) The overarching purpose of this MCA is to support communities to be resilient by enhancing their capacity and capability to manage civil defence emergencies. |
16,238 | 11,566 | 27,804 |
Departmental Output Expenses |
|||
Community Awareness and Readiness This category is limited to the development and delivery of long-term national programmes to raise individual and community awareness and preparedness. |
1,938 | 746 | 2,684 |
Emergency Sector and Support and Development This category is limited to developing and implementing operational policies and projects, advice, assistance and information to the civil defence and emergency management sector. |
5,644 | 1,487 | 7,131 |
Management of Emergencies This category is limited to management of national emergency readiness, response and recovery, including support to local civil defence emergency management organisations, maintaining the National Crisis Management Centre in a state of readiness, national training and exercises, coordination and management of central government's response and recovery activities and administration of related expenses. |
7,713 | 9,745 | 17,458 |
Policy Advice - Emergency Management This category is limited to the provision of advice (including second opinion advice and contributions to policy advice led by other agencies) to support decision-making by Ministers on government policy matters relating to civil defence emergency matters. |
943 | (412) | 531 |
Government House Buildings and Assets MCA (M52) The overarching purpose of this appropriation is maintaining the Government House buildings and related assets in Wellington and Auckland to the standards necessary to fulfil their constitutional, ceremonial and community roles. |
3,292 | 250 | 3,542 |
Non-Departmental Other Expenses |
|||
Depreciation of Crown Assets This category is limited to depreciation expenses on the Government House buildings and related assets. |
1,962 | (200) | 1,762 |
Government House - Maintenance This category is limited to the ongoing maintenance of the Government House buildings and related assets, and the grounds on which they are located. |
600 | 200 | 800 |
Non-Departmental Capital Expenditure |
|||
Government House - Capital Investment This category is limited to investment necessary to preserve the functionality and value of the Government House buildings and related assets. |
730 | 250 | 980 |
Policy Advice and Support Services MCA (M52) The overarching purpose of this appropriation is to provide policy advice to support decision-making by the Prime Minister and the Cabinet and provide support services to the Prime Minister, Cabinet and its committees, the Executive Council, and the Governor General. |
25,333 | 3,436 | 28,769 |
Departmental Output Expenses |
|||
National Security Priorities and Intelligence Coordination This category is limited to leadership and coordination around national security matters, leading collaboration within the New Zealand intelligence community and providing intelligence assessments to support national security priorities. |
10,513 | 379 | 10,892 |
Policy Advice - Prime Minister and Cabinet This category is limited to the provision of advice (including second opinion advice and contributions to policy advice led by other agencies) to support decision-making by the Prime Minister and the Cabinet. |
3,996 | 3,318 | 7,314 |
Science Advisory Committee This category is limited to the purchase of high-quality scientific advice to the Prime Minister. |
675 | 50 | 725 |
Support Services to the Governor-General and Maintenance of the Official Residences This category is limited to financial, administrative, communications and advisory services for the Governor-General; and services to maintain the Governor-General's residences. |
4,209 | (189) | 4,020 |
Support, Secretariat and Coordination Services This category is limited to the provision of services to Ministers to enable them to discharge their portfolio (other than policy decision-making) responsibilities including support for the coordination of the Government's legislation programme; secretariat services to the Executive Council, Cabinet and its committees; and administration of the New Zealand Honours system. |
5,940 | (122) | 5,818 |
Total Multi-Category Expenses and Capital Expenditure |
44,863 | 15,252 | 60,115 |
Total Annual and Permanent Appropriations |
69,642 | 67,952 | 137,594 |
Multi-Year Appropriations#
Type, Title, Scope and Period of Appropriations | Appropriations, Adjustments and Use | $000 |
---|---|---|
Non-Departmental Output Expenses |
||
Regenerate Christchurch (M85) This appropriation is limited to establishment costs and the development of strategies and planning activities, with communities, stakeholders and decision-makers, for the regeneration of areas in Christchurch.Commences: 01 July 2016 Expires: 30 June 2021 |
Original Appropriation | 20,000 |
Adjustments to 2016/17 | 1,073 | |
Adjustments for 2017/18 | - | |
Adjusted Appropriation | 21,073 | |
Actual to 2016/17 Year End | 4,000 | |
Estimated Actual for 2017/18 | 4,000 | |
Estimated Actual for 2018/19 | 5,073 | |
Estimated Appropriation Remaining | 8,000 |
Total Annual and Permanent Appropriations and Multi-Year Appropriation Forecasts#
2017/18 | |||
---|---|---|---|
Estimates Budget $000 |
Supplementary Estimates Budget $000 |
Total Budget $000 |
|
Total Annual and Permanent Appropriations | 69,642 | 67,952 | 137,594 |
Total MYA Non-Departmental Output Expenses Forecasts | 4,000 | - | 4,000 |
Total Annual and Permanent Appropriations and Multi-Year Appropriation Forecasts |
73,642 | 67,952 | 141,594 |
Capital Injection Authorisations#
2017/18 | |||
---|---|---|---|
Estimates Budget $000 |
Supplementary Estimates Budget $000 |
Total Budget $000 |
|
Department of the Prime Minister and Cabinet - Capital Injection (M52) | 200 | 100 | 300 |
Supporting Information#
Part 1 - Vote as a Whole#
1.2 - Trends in the Vote
Summary of Financial Activity
2017/18 | |||||
---|---|---|---|---|---|
Supplementary Estimates | |||||
Estimates $000 |
Departmental Transactions $000 |
Non-Departmental Transactions $000 |
Total Transactions $000 |
Total $000 |
|
Appropriations |
|||||
Output Expenses | 16,030 | 752 | - | 752 | 16,782 |
Benefits or Related Expenses | - | N/A | - | - | - |
Borrowing Expenses | - | - | - | - | - |
Other Expenses | 12,449 | - | 36,698 | 36,698 | 49,147 |
Capital Expenditure | 300 | 250 | 15,000 | 15,250 | 15,550 |
Intelligence and Security Department Expenses and Capital Expenditure | - | - | N/A | - | - |
Multi-Category Expenses and Capital Expenditure (MCA) | |||||
Output Expenses | 41,571 | 15,002 | - | 15,002 | 56,573 |
Other Expenses | 2,562 | - | - | - | 2,562 |
Capital Expenditure | 730 | N/A | 250 | 250 | 980 |
Total Appropriations |
73,642 | 16,004 | 51,948 | 67,952 | 141,594 |
Crown Revenue and Capital Receipts |
|||||
Tax Revenue | - | N/A | - | - | - |
Non-Tax Revenue | 150 | N/A | - | - | 150 |
Capital Receipts | - | N/A | - | - | - |
Total Crown Revenue and Capital Receipts |
150 | N/A | - | - | 150 |
Part 2 - Details of Departmental Appropriations#
2.1 - Departmental Output Expenses#
Canterbury Earthquake Recovery (M85)
Scope of Appropriation
Expenses and Revenue
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Total Appropriation | 12,030 | 160 | 12,190 |
Revenue from the Crown | 12,030 | (25) | 12,005 |
Revenue from Others | - | 185 | 185 |
Reasons for Change in Appropriation
This appropriation increased by $160,000 to $12.190 million for 2017/18 due to:
- $250,000 for the distribution of the retention of underspend from 2016/17
- $185,000 revenue for the sub-lease of Christchurch property, and
- $275,000 reduction due to the transfer of funding to Land Information New Zealand for staff and legal costs.
Support for Inquiry into EQC (M86)#
Scope of Appropriation#
Expenses and Revenue#
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Total Appropriation | - | 592 | 592 |
Revenue from the Crown | - | 592 | 592 |
Revenue from Others | - | - | - |
What is Intended to be Achieved with this Appropriation#
This appropriation is intended to achieve effective support for the Inquiry into the Earthquake Commission (EQC).
How Performance will be Assessed and End of Year Reporting Requirements#
2017/18 | |||
---|---|---|---|
Performance Measures | Estimates Standard |
Supplementary Estimates Standard |
Total Standard |
Inquiry's satisfaction with the Support for Inquiry into EQC, as measured using the Common Satisfaction Survey (see Note 1) is at least: |
New Measure | 6 | 6 |
Note 1 - The Common Satisfaction Survey measures the Inquiry's satisfaction with the quality, timeliness and value for money of policy advice on a scale from 1 to 10, where 1 means fell well short of expectations and 10 means far exceeded expectations.
End of Year Performance Reporting#
Performance information for this appropriation will be reported by the Department of the Prime Minister and Cabinet in the 2017/18 Annual Report.
Reasons for Change in Appropriation#
This is a new appropriation of $592,000 in 2017/18 to provide support for the Inquiry into EQC.
2.3 - Departmental Capital Expenditure and Capital Injections#
Department of the Prime Minister and Cabinet - Capital Expenditure PLA (M52)#
Scope of Appropriation
Capital Expenditure
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Forests/Agricultural | - | - | - |
Land | - | - | - |
Property, Plant and Equipment | 250 | 250 | 500 |
Intangibles | - | - | - |
Other | 50 | - | 50 |
Total Appropriation |
300 | 250 | 550 |
Reasons for Change in Appropriation
This appropriation increased by $250,000 to $550,000 for 2017/18 due to an increase in the expected costs of replacement of the department's fixed assets according to the approved capital plan.
Capital Injections and Movements in Departmental Net Assets
Department of the Prime Minister and Cabinet
Details of Net Asset Schedule | 2017/18 Main Estimates Projections $000 |
2017/18 Supplementary Estimates Projections $000 |
Explanation of Projected Movements in 2017/18 |
---|---|---|---|
Opening Balance | 7,997 | 7,997 | Supplementary Estimates opening balance reflects the audited results as at 30 June 2017. |
Capital Injections | 200 | 300 | Capital injection for the direction, coordination and provision of intelligence assessments to support national intelligence priorities, and to provide support for the Inquiry into EQC. |
Capital Withdrawals | - | - | |
Surplus to be Retained (Deficit Incurred) | - | - | |
Other Movements | - | - | |
Closing Balance |
8,197 | 8,297 |
Part 3 - Details of Non-Departmental Appropriations#
3.1 - Non-Departmental Output Expenses#
Regenerate Christchurch (M85)
Scope of Appropriation and Expenses
Type, Title, Scope and Period of Appropriations | Appropriations, Adjustments and Use | $000 |
---|---|---|
Regenerate Christchurch (M85) This appropriation is limited to establishment costs and the development of strategies and planning activities, with communities, stakeholders and decision-makers, for the regeneration of areas in Christchurch.Commences: 01 July 2016 Expires: 30 June 2021 |
Original Appropriation | 20,000 |
Adjustments to 2016/17 | 1,073 | |
Adjustments for 2017/18 | - | |
Adjusted Appropriation | 21,073 | |
Actual to 2016/17 Year End | 4,000 | |
Estimated Actual for 2017/18 | 4,000 | |
Estimated Actual for 2018/19 | 5,073 | |
Estimated Appropriation Remaining | 8,000 |
How Performance will be Assessed and End of Year Reporting Requirements
2017/18 | |||
---|---|---|---|
Performance Measures | Estimates Standard |
Supplementary Estimates Standard |
Total Standard |
Regenerate Christchurch will lead and contribute to the regeneration of Christchurch in accordance with its purpose, objective and functions set out in the Greater Christchurch Regeneration Act 2016, and with the responsible Minister's and Christchurch City Mayor's Letter of Expectations (see Note 1) |
Achieved | Expired measure | Expired measure |
Regenerate Christchurch's achievement in leading and contributing to the regeneration of Christchurch, as measured using the performance targets in its annual Statement of Performance Expectations (see Note 2), is at least: |
New measure | 60% | 60% |
Note 1 - In the absence of Regenerate Christchurch's final work programme, the measure and standard have been updated to ensure Regenerate Christchurch meets its statutory requirements.
Note 2 - This measure has been updated to ensure Regenerate Christchurch is publicly accountable through meeting at least 60 per cent of its performance targets in its annual Statement of Performance Expectations 2017/18 (pages 1 and 3). As Regenerate Christchurch is relatively new, we expect the targeted amount for achievement to increase year-on-year.
3.4 - Non-Departmental Other Expenses#
Contributions to Local Authorities Following an Emergency Event (M11)#
Scope of Appropriation
Expenses
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Total Appropriation | - | 580 | 580 |
What is Intended to be Achieved with this Appropriation
This appropriation is intended to achieve financial support to local authorities in an emergency in the form of contributions to local authority disaster relief funds or special policy funding for programmes of work that will decrease the likelihood of a similar emergency occurring again.
How Performance will be Assessed and End of Year Reporting Requirements
An exemption was granted under section 15D(2)(b)(ii) of the Public Finance Act 1989 on the basis that end-of-year performance information for the appropriation or category is not likely to be informative because payments from this appropriation are for discretionary financial support to local authorities following an emergency event, such as contributions to disaster relief funds, as prescribed in the current Guide to the National Civil Defence Emergency Management Plan.
Reasons for Change in Appropriation
This appropriation increased by $580,000 for 2017/18 due to:
- $500,000 for this new appropriation to support local authorities following an emergency (which replaces funding for this purpose previously included in the now disestablished appropriation 'Emergency Expenses'), and
- $80,000 transfer of funding from the Ministry of Business, Innovation and Employment as a contribution to disaster relief payments made by a local authority.
Crown Contribution for Christ Church Cathedral Reinstatement (M85)#
Scope of Appropriation#
Expenses#
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Total Appropriation | - | 10,000 | 10,000 |
What is Intended to be Achieved with this Appropriation#
This appropriation is intended to achieve implementation of the Crown's offer to support the reinstatement of Christ Church Cathedral.
How Performance will be Assessed and End of Year Reporting Requirements#
2017/18 | |||
---|---|---|---|
Performance Measures | Estimates Standard |
Supplementary Estimates Standard |
Total Standard |
Terms and criteria for payment of the $10 million contribution to support the Christ Church Cathedral reinstatement have been met and the grant has been paid. |
New measure | Achieved | Achieved |
End of Year Performance Reporting#
Performance information for this appropriation will be included in the Department of the Prime Minister and Cabinet's 2017/18 Annual Report.
Reasons for Change in Appropriation#
This is a new appropriation of $10 million in 2017/18 to provide a contribution towards the reinstatement of Christ Church Cathedral.
Emergency Expenses (M11)#
Scope of Appropriation#
Expenses#
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Total Appropriation | 2,000 | (2,000) | - |
Reasons for Change in Appropriation#
This appropriation was disestablished at the completion of the 2016/17 financial year and replaced by two new appropriations to better suit the purpose of these payments. The new appropriations are 'Local Authority Emergency Expenses PLA' and 'Contributions to Local Authorities Following an Emergency Event'.
Emergency Management Preparedness Grants (M11)#
Scope of Appropriation#
Expenses#
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Total Appropriation | 889 | 152 | 1,041 |
Reasons for Change in Appropriation#
This appropriation increased by $152,000 to $1.041 million for 2017/18 due to a transfer from 2016/17 to support local authorities' emergency resilience programmes.
Fair Value Write-down of Suspensory Loan for Christ Church Cathedral Reinstatement (M85)#
Scope of Appropriation#
Expenses#
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Total Appropriation | - | 15,000 | 15,000 |
What is Intended to be Achieved with this Appropriation#
This appropriation is intended to achieve the write-down of the suspensory loan for Christ Church Cathedral reinstatement.
How Performance will be Assessed and End of Year Reporting Requirements#
An exemption was granted under section 15D(2)(b)(ii) of the Public Finance Act 1989 on the basis that any expenses associated with fair value write-down are non-cash and for accounting purposes only, and so any performance information would not likely be informative.
Reasons for Change in Appropriation#
This is a new appropriation of $15 million in 2017/18 to support the costs of write-down of the suspensory loan for Christ Church Cathedral reinstatement.
Governor-General's Programme PLA (M52)#
Scope of Appropriation#
Expenses#
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Total Appropriation | 1,139 | 100 | 1,239 |
Reasons for Change in Appropriation#
This appropriation increased by $100,000 to $1.239 million for 2017/18 and outyears due to increased expenditure reflecting changes to the Governor-General's programme.
Governor-General's Salary and Allowance PLA (M52)#
Scope of Appropriation#
Expenses#
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Total Appropriation | 400 | 100 | 500 |
Reasons for Change in Appropriation#
This appropriation increased by $100,000 to $500,000 for 2017/18 and outyears due to an expected increase in salary costs.
Governor-General's travel outside New Zealand PLA (M52)#
Scope of Appropriation#
Expenses#
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Total Appropriation | 307 | 100 | 407 |
Reasons for Change in Appropriation#
This appropriation increased by $100,000 to $407,000 for 2017/18 and outyears due to forecast increases in the costs of the Governor-General's approved overseas travel programme.
Inquiry into EQC (M86)#
Scope of Appropriation#
Expenses#
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Total Appropriation | - | 216 | 216 |
What is Intended to be Achieved with this Appropriation#
This appropriation is intended to achieve the timely and efficient payment of fees and expenses for the Inquiry Chair and Members related to the Inquiry into the Earthquake Commission (EQC).
How Performance will be Assessed and End of Year Reporting Requirements#
An exemption was granted under section 15D(2)(b)(iii) of the Public Finance Act 1989 on the basis that the amount (or annual average equivalent) of the appropriation is less than $5 million for expenses.
Reasons for Change in Appropriation#
This is a new appropriation of $216,000 in 2017/18 to fund payment of fees and expenses for the Inquiry into EQC.
Local Authority Emergency Expenses PLA (M11)#
Scope of Appropriation#
Expenses#
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Total Appropriation | 5,000 | 10,000 | 15,000 |
Reasons for Change in Appropriation#
This appropriation increased by $10 million to $15 million for 2017/18 due to the ongoing assessment of expected reimbursements to local authorities for expenses incurred by them in connection with emergency events.
Rehabilitation of Kaikoura Harbour (M11)#
Scope of Appropriation#
Expenses#
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Total Appropriation | 720 | 1,750 | 2,470 |
Reasons for Change in Appropriation#
This appropriation increased by $1.750 million to $2.470 million for 2017/18 due to transfers from the 2016/17 year to complete the substantial programme of work to rehabilitate Kaikoura Harbour.
Remuneration of Commissioners of Intelligence Warrants PLA (M52)#
Scope of Appropriation#
Expenses#
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Total Appropriation | 74 | 100 | 174 |
What is Intended to be Achieved with this Appropriation#
This permanent appropriation provides for payment to Commissioners of Intelligence Warrants of salaries and allowances as determined by the Remuneration Authority.
How Performance will be Assessed and End of Year Reporting Requirements#
An exemption was granted under section 15D(2)(b)(ii) of the Public Finance Act 1989 on the basis that end-of-year performance information for the appropriation or category is not likely to be informative, because this appropriation is solely for payments of salaries and allowances to the Commissioners of Intelligence Warrants.
Reasons for Change in Appropriation#
This appropriation increased by $100,000 to $174,000 for 2017/18 due to increased expenditure as a result of the appointment of an additional Commissioner. Note that this appropriation has a different title and scope from its predecessor (Fees for the Commissioner of Security Warrants PLA), due to the relevant legislation having been amended in 2017.
Restoration of Kaikoura District Three Waters Network (M11)#
Scope of Appropriation#
Expenses#
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Total Appropriation | 1,800 | 600 | 2,400 |
How Performance will be Assessed and End of Year Reporting Requirements#
2017/18 | |||
---|---|---|---|
Performance Measures | Estimates Standard |
Supplementary Estimates Standard |
Total Standard |
Additional resilience or other improvements to support the restoration of infrastructure systems are carried out as recommended by the Infrastructure and Facilities Rebuild Steering Group |
Achieved | Expired measure | Expired measure |
Additional work scope over and above a "like for like" repair or replacement must be recommended by the Kaikoura Rebuild Steering Group and must meet the requirements of the Memorandum of Understanding: drawdown of restoration of three waters appropriation (see Note 1) |
New measure | Achieved | Achieved |
Note 1 - "Achieved" would be supported by the following - a copy of the Memorandum of Understanding, a copy of the steering group minute, a copy of the business case for the project/s or betterment work scope.
End of Year Performance Reporting#
Performance information for this appropriation will be reported by the Minister of Civil Defence in a report appended to the Department of the Prime Minister and Cabinet's 2017/18 Annual Report.
Reasons for Change in Appropriation#
This appropriation increased by $600,000 to $2.400 million for 2017/18 due to transfers of funds from 2016/17 to support the restoration of the Kaikoura District Council's essential infrastructure assets.
3.5 - Non-Departmental Capital Expenditure#
Suspensory Loan for Christ Church Cathedral Reinstatement (M85)#
Scope of Appropriation
Capital Expenditure
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Total Appropriation | - | 15,000 | 15,000 |
What is Intended to be Achieved with this Appropriation
This appropriation is intended to achieve the implementation of the Crown's offer to support the reinstatement of Christ Church Cathedral.
How Performance will be Assessed and End of Year Reporting Requirements
2017/18 | |||
---|---|---|---|
Performance Measures | Estimates Standard |
Supplementary Estimates Standard |
Total Standard |
Terms and criteria for advancing the $15 million suspensory loan to support the Christ Church Cathedral reinstatement have been met and the suspensory loan has been advanced. |
New measure | Achieved | Achieved |
End of Year Performance Reporting
Performance information for this appropriation will be included in the Department of the Prime Minister and Cabinet's 2017/18 Annual Report.
Reasons for Change in Appropriation
This is a new appropriation of $15 million in 2017/18 to provide a suspensory loan to support the reinstatement of Christ Church Cathedral.
Part 4 - Details of Multi-Category Expenses and Capital Expenditure#
Multi-Category Expenses and Capital Expenditure#
Emergency Management (M11)
Overarching Purpose Statement
Scope of Appropriation
Departmental Output Expenses
Community Awareness and ReadinessThis category is limited to the development and delivery of long-term national programmes to raise individual and community awareness and preparedness.
Emergency Sector and Support and Development
This category is limited to developing and implementing operational policies and projects, advice, assistance and information to the civil defence and emergency management sector.
Management of Emergencies
This category is limited to management of national emergency readiness, response and recovery, including support to local civil defence emergency management organisations, maintaining the National Crisis Management Centre in a state of readiness, national training and exercises, coordination and management of central government's response and recovery activities and administration of related expenses.
Policy Advice - Emergency Management
This category is limited to the provision of advice (including second opinion advice and contributions to policy advice led by other agencies) to support decision-making by Ministers on government policy matters relating to civil defence emergency matters.
Expenses, Revenue and Capital Expenditure
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Total Appropriation |
16,238 | 11,566 | 27,804 |
Departmental Output Expenses |
|||
Community Awareness and Readiness | 1,938 | 746 | 2,684 |
Emergency Sector and Support and Development | 5,644 | 1,487 | 7,131 |
Management of Emergencies | 7,713 | 9,745 | 17,458 |
Policy Advice - Emergency Management | 943 | (412) | 531 |
Funding for Departmental Output Expenses |
|||
Revenue from the Crown |
16,008 | 9,166 | 25,174 |
Community Awareness and Readiness | 1,915 | 746 | 2,661 |
Emergency Sector and Support and Development | 5,523 | (113) | 5,410 |
Management of Emergencies | 7,627 | 8,945 | 16,572 |
Policy Advice - Emergency Management | 943 | (412) | 531 |
Revenue from Others |
230 | 2,400 | 2,630 |
Community Awareness and Readiness | 23 | - | 23 |
Emergency Sector and Support and Development | 121 | 1,600 | 1,721 |
Management of Emergencies | 86 | 800 | 886 |
What is Intended to be Achieved with each Category and How Performance will be Assessed
2017/18 | |||
---|---|---|---|
Assessment of Performance | Estimates Standard |
Supplementary Estimates Standard |
Total Standard |
Departmental Output Expenses |
|||
Emergency Sector and Support and Development |
|||
This category is intended to develop and implement operational policies and projects, advice, assistance and information to the civil defence and emergency management sector |
|||
The number of Director Guidelines, Technical Standards, Codes and the other civil defence emergency management information publications that are either reviewed or published will be at least: |
2 | Expired measure | Expired measure |
The number of Director Guidelines, Technical Standards and Codes that are either reviewed or published (see Note 1) will be at least: |
New Measure | 2 | 2 |
Satisfaction assessed as 'Good' or 'Very Good', in relation to: (see Note 2) |
|||
|
80% | Expired measure | Expired measure |
|
80% | Expired measure | Expired measure |
Satisfaction is at least 6 in relation to the two measures below (see Note 3): |
|||
|
New measure | 6 | 6 |
|
New measure | 6 | 6 |
The number of CDEM initiatives developed or implemented in partnership with public sector, private sector and/or the not-for-profit sector will be between: |
5-6 | Expired measure | Expired measure |
The number of CDEM initiatives developed or implemented in partnership with the public sector, private sector and/or the not-for-profit sector will be at least: |
New measure | 5 | 5 |
Management of Emergencies |
|||
This category is intended to enable management of national emergency readiness, response and recovery operations. |
|||
National warning distribution list - accuracy of contact details (at each warning or test), at least: |
95% | Expired measure | Expired measure |
An initial National Warning issued within 15 minutes of the Duty Manager's decision to issue a National Warning |
100% | Expired measure | Expired measure |
An initial National Warning is issued within 20 minutes of the Duty Manager's decision to issue a National Warning |
New measure | 100% | 100% |
National Crisis Management Centre managed, during activations, with: |
|||
|
100% | Expired measure | Expired measure |
|
New measure | Achieved | Achieved |
|
95% | Expired measure | Expired measure |
|
New measure | 95% | 95% |
|
100% | Expired measure | Expired measure |
National Crisis Management Centre activations reviewed: |
|||
|
100% | Expired measure | Expired measure |
|
100% | Expired measure | Expired measure |
|
New measure | Achieved | Achieved |
Project management regarding Cell Broadcast Alerting is in accordance with the project plan and milestones signed off by project governance (see Note 4) |
Achieved | Expired measure | Expired measure |
Note 1 - Relevant publications are those found on our publications list website http://www.civildefence.govt.nz/resource/publications
Note 2 - Satisfaction performance measure involves a five point scale numerical 1 - 5 (with '5' the highest rating) or qualitative: Very Good, Good, Satisfied, Poor and Very Poor.
Note 3 - Satisfaction performance measure involves a 10-point scale, where 1 means fell well short of expectations and 10 means far exceeded expectations.
Note 4 - The project milestones regarding Cell Broadcast Alerting are met as per project plan.
Reasons for Change in Appropriation
This appropriation increased by $11.566 million to $27.804 million mainly due to:
- $7.797 million for the Cell Broadcast Alerting project
- $1.600 million funding received from the Ministry of Foreign Affairs and Trade to support emergency resilience programmes
- $1.500 million for Kaikoura earthquake initiatives
- $745,000 for distribution of retained underspends from 2016/17
- $176,000 for the recalibration of overhead costs within the department, and
- $100,000 to support capability and capacity improvements.
Government House Buildings and Assets (M52)#
Overarching Purpose Statement#
Scope of Appropriation#
Non-Departmental Other Expenses
Depreciation of Crown AssetsThis category is limited to depreciation expenses on the Government House buildings and related assets.
Government House - Maintenance
This category is limited to the ongoing maintenance of the Government House buildings and related assets, and the grounds on which they are located.
Non-Departmental Capital Expenditure
Government House - Capital InvestmentThis category is limited to investment necessary to preserve the functionality and value of the Government House buildings and related assets.
Expenses, Revenue and Capital Expenditure#
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Total Appropriation |
3,292 | 250 | 3,542 |
Non-Departmental Other Expenses |
|||
Depreciation of Crown Assets | 1,962 | (200) | 1,762 |
Government House - Maintenance | 600 | 200 | 800 |
Non-Departmental Capital Expenditure |
|||
Government House - Capital Investment | 730 | 250 | 980 |
Reasons for Change in Appropriation#
This appropriation increased by $250,000 to $3.542 million for 2017/18 due to net expense transfers from 2016/17 to continue to support the programme of maintenance and capital investment in Government House.
Policy Advice and Support Services (M52)#
Overarching Purpose Statement#
Scope of Appropriation#
Departmental Output Expenses
National Security Priorities and Intelligence CoordinationThis category is limited to leadership and coordination around national security matters, leading collaboration within the New Zealand intelligence community and providing intelligence assessments to support national security priorities.
Policy Advice - Prime Minister and Cabinet
This category is limited to the provision of advice (including second opinion advice and contributions to policy advice led by other agencies) to support decision-making by the Prime Minister and the Cabinet.
Science Advisory Committee
This category is limited to the purchase of high-quality scientific advice to the Prime Minister.
Support Services to the Governor-General and Maintenance of the Official Residences
This category is limited to financial, administrative, communications and advisory services for the Governor-General; and services to maintain the Governor-General's residences.
Support, Secretariat and Coordination Services
This category is limited to the provision of services to Ministers to enable them to discharge their portfolio (other than policy decision-making) responsibilities including support for the coordination of the Government's legislation programme; secretariat services to the Executive Council, Cabinet and its committees; and administration of the New Zealand Honours system.
Expenses, Revenue and Capital Expenditure#
2017/18 | |||
---|---|---|---|
Estimates $000 |
Supplementary Estimates $000 |
Total $000 |
|
Total Appropriation |
25,333 | 3,436 | 28,769 |
Departmental Output Expenses |
|||
National Security Priorities and Intelligence Coordination | 10,513 | 379 | 10,892 |
Policy Advice - Prime Minister and Cabinet | 3,996 | 3,318 | 7,314 |
Science Advisory Committee | 675 | 50 | 725 |
Support Services to the Governor-General and Maintenance of the Official Residences | 4,209 | (189) | 4,020 |
Support, Secretariat and Coordination Services | 5,940 | (122) | 5,818 |
Funding for Departmental Output Expenses |
|||
Revenue from the Crown |
25,303 | 1,571 | 26,874 |
National Security Priorities and Intelligence Coordination | 10,513 | (176) | 10,337 |
Policy Advice - Prime Minister and Cabinet | 3,996 | 2,073 | 6,069 |
Science Advisory Committee | 675 | - | 675 |
Support Services to the Governor-General and Maintenance of the Official Residences | 4,179 | (189) | 3,990 |
Support, Secretariat and Coordination Services | 5,940 | (137) | 5,803 |
Revenue from Others |
30 | 1,865 | 1,895 |
National Security Priorities and Intelligence Coordination | - | 555 | 555 |
Policy Advice - Prime Minister and Cabinet | - | 1,245 | 1,245 |
Science Advisory Committee | - | 50 | 50 |
Support Services to the Governor-General and Maintenance of the Official Residences | 30 | - | 30 |
Support, Secretariat and Coordination Services | - | 15 | 15 |
How Performance will be Assessed for this Appropriation#
2017/18 | |||
---|---|---|---|
Assessment of Performance | Estimates Standard |
Supplementary Estimates Standard |
Total Standard |
Increasing proportion of Better Public Services result areas on track to achieve their targets |
7 | Expired measure | Expired measure |
Overall service quality of Public Services improves over time |
0.75 | Expired measure | Expired measure |
The satisfaction of the Prime Minister and the Governor-General, with the quality of services and/or support provided by the Department of the Prime Minister and Cabinet is at least: |
New measure | 6 | 6 |
What is Intended to be Achieved with each Category and How Performance will be Assessed#
2017/18 | |||
---|---|---|---|
Assessment of Performance | Estimates Standard |
Supplementary Estimates Standard |
Total Standard |
Departmental Output Expenses |
|||
National Security Priorities and Intelligence Coordination |
|||
This category is intended to ensure that New Zealand has world-class processes in place to deal with national security events and emergencies, and an intelligence community that is trusted, integrated, customer-oriented and crucial to building national resilience |
|||
Advice and guidance on policies and preparation for strengthening national security is fully integrated, timely and of high quality |
Meets expectations | Expired measure | Expired measure |
Assessments provided to inform Ministers and senior officials of risks and opportunities relating to New Zealand interests are accurate and succinct |
98% | Expired measure | Expired measure |
Ministers and senior officials have confidence that assessments provided are of high quality and of policy relevance to New Zealand, assessed as the proportion of stakeholders whose expectations are met or exceeded |
90% | Expired measure | Expired measure |
All-of-government responses to national crises and events are effectively coordinated and managed, assessed as the proportion of stakeholders whose expectations are met or exceeded |
90% | Expired measure | Expired measure |
The satisfaction of the Prime Minister with the leadership and coordination around national security matters, leading collaboration within the New Zealand intelligence community and providing intelligence assessments to support national security priorities (see Note 1) is at least: |
New measure | 6 | 6 |
Support Services to the Governor-General and Maintenance of the Official Residences |
|||
This category is intended to ensure the Governor-General is appropriately advised and supported in carrying out his or her constitutional, ceremonial, community and international roles. This is intended to be achieved through effective advisory, operational, financial, administrative and communications support being provided to the Governor-General. It is also intended to ensure that the official residences are appropriately maintained. |
|||
Support to the Governor-General is efficient and effective |
Governor-General's expectations met or exceeded | Expired measure | Expired measure |
Events at the Government House are well organised |
Governor-General's expectations met or exceeded | Expired measure | Expired measure |
Management of the Governor-General's domestic and international programme is appropriate and well balanced |
Governor-General's expectations met or exceeded | Expired measure | Expired measure |
The satisfaction of the Governor-General with services provided as measured using the Common Satisfaction Survey (see Note 1) is at least: |
New measure | 6 | 6 |
Support, Secretariat and Coordination Services |
|||
This category is intended to achieve the provision of effective support to the Prime Minister and Ministers to enable them to discharge their portfolio responsibilities, and to support the coordination of the Government's legislation programme, provide secretarial services to the Executive Council, Cabinet, and its committees, and to administer the New Zealand Honours system. |
|||
Formal feedback from the Governor-General and the Prime Minister on services provided |
Overall expectations are met or exceeded | Expired measure | Expired measure |
The satisfaction of the Governor-General with services provided as measured using the Common Satisfaction Survey (see Note 1) is at least: |
New measure | 6 | 6 |
The satisfaction of the Prime Minister with services provided as measured using the Common Satisfaction Survey (see Note 1) is at least: |
New measure | 6 | 6 |
Note 1 - Satisfaction performance measure involves a 10-point scale, where 1 means fell well short of expectations and 10 means far exceeded expectations.
Reasons for Change in Appropriation#
This appropriation increased by $3.436 million to $28.769 million for 2017/18 due to:
- $1.865 million for revenue received from other agencies to support the Policy Project and the Science Advisory Committee, and the establishment of development programmes for the national security workforce, as well as recoveries of secondment costs
- $955,000 for distributions of retained underspends from 2016/17
- $350,000 for transfers from 2016/17 due to delays in projects and uncertainties around timing of expenditure
- $176,000 for the recalibration of overhead costs within the department, and
- $90,000 transfer of funding from Government Communications Security Bureau for the permanent transfer of staff.