Part 6 - Details and Expected Results for Capital Expenditure
Part 6.1 - Departmental Capital Expenditure
Ministry of Pacific Island Affairs - Capital Expenditure PLA (M50)
Scope of Appropriation
Capital Expenditure
| 2011/12 | 2012/13 | ||
|---|---|---|---|
| Budgeted $000 | Estimated Actual $000 | Budget $000 | |
| Forests/Agricultural | - | - | - |
| Land | - | - | - |
| Property, Plant and Equipment | 80 | 80 | 100 |
| Intangibles | 20 | 20 | - |
| Other | - | - | - |
Total Appropriation | 100 | 100 | 100 |
Reasons for Change in Appropriation
The appropriation was budgeted at $100,000 for the 2011/12 year to be used in the regular replacement of equipment, the upgrading of network computer equipment, and relocation costs in connection with the Christchurch office. In the 2012/13 year, the funding is provided primarily to allow for leasehold improvements in connection with a possible move of the Wellington office.